2008

SD8015 : Turbine Convoy enroute to Scout Moor

taken 16 years ago, near to Summerseat, Bury, England

Turbine Convoy enroute to Scout Moor
Turbine Convoy enroute to Scout Moor
Three tower sections for Turbine No 23 head North along the M66 en route to
the Scout Moor Wind Farm.

SD8318 : Scout Moor Turbine Towers 15 and 21
SD7919 : Turbine tower section passing Edenfield Primary School
SD8418 : The very first completed wind turbine on Scout Moor
SD8418 : Freezing weather conditions on Scout Moor
SD8417 : Turbine Tower No 10 under construction
SD8417 : Working on the hub 60 metres up.

Turbine details: Tower Height: 60m
Blade Length: 40m Total Max Height: 100m
Manufacturer: Nordex
Model: N80

Scout Moor Wind Farm Construction Picture Gallery
Link

Following a public inquiry held in 2004, planning consent was granted by the Secretary of State on the 25th May 2005 for the building of Scout Moor Wind Farm.
Construction of the wind turbines began back in November 2007 at Turbine No 16.
By June 2008 engineers had constructed 26 wind turbine towers and installed 78 turbine blades 450 metres above sea level on Scout Moor amid adverse weather conditions of thick fog, gale force winds, torrential rain, snow and ice during the winter months of 2008.

On the 25th of September 2008 dignitaries from across the North West were invited to the official opening of the Scout Moor wind farm.
Children from Edenfield Primary School, who have enjoyed lessons based around the wind farm, were on hand to cut the ribbon at Turbine No 22. Link
Head Teacher at Edenfield Primary School, Janet Reidy, said: "It was superb for the children to be involved after all the work they had done about the wind farm in their lessons.
I think they will all remember this in future years and now they know what it's like to be film stars with all the camera crews there!"

Richard Dibley, wind power development manager at Peel, said at the opening: "We have welcomed people here today to thank them for their patience and understanding during the construction period and for them to see the wind farm in action at close quarters. I think we have chosen the perfect site here as it is more than 50% windier up here than it is in the surrounding area. These turbines will be generating power for years to come using a natural resource that will never run out."

Creative Commons Licence [Some Rights Reserved]   © Copyright Paul Anderson and licensed for reuse under this Creative Commons Licence.
Category: Road > Motorway
1:50,000 Modern Day Landranger(TM) Map © Crown Copyright
+
+
1:50,000 Modern Day Landranger(TM) Map © Crown Copyright
TIP: Click the map for more Large scale mapping
Grid Square
SD8015, 67 images   (more nearby 🔍)
Photographer
Paul Anderson   (more nearby)
Date Taken
Tuesday, 20 May, 2008   (more nearby)
Submitted
Tuesday, 20 May, 2008
Subject Location
OSGB36: geotagged! SD 804 150 [100m precision]
WGS84: 53:37.8801N 2:17.8718W
Camera Location
OSGB36: geotagged! SD 802 151
View Direction
Southeast (about 135 degrees)
Clickable map
+
NW N NE
W Go E
SW S SE
Image classification(about): Geograph
This page has been viewed about 375 times
You are not logged in login | register